3/29/18 15:05 REMEMBER TO RELOAD _ for latest version                  
rjk   Coordination         Supporting       6 to 1 6 to 7 6 to 1 6 to 2:30 6 to 1  
* = At Rich's discretion  ** = At Alex's discretion  *** = at Ron's discretion  
CMTF Floor scrub – 4/5 and 4/19
NML Floor scrub – 4/10
CMTF Clean Room – 4/25
                            M Tu W Th F S S
Machine / Job Priority for This Week Completed date Comments/Details DF KK CR DL CE EL   DF KK DL CE CR EL   2 3 4 5 30 31 1
FAST/IOTA                                                
Inside Cave/Tunnel Work                                                
Curt's FAST/IOTA Click on this entry to see worklist 1   Priority list below[1] 1               X           1 1 1 1 1    
Lambertson magnet 1   Priority list below[2] 1               X           1 1 1 1 1    
Certifiy Radiabeam IOTA nonlinear magnet chamber 2   Lucy  2                           2 2 2 2 2    
Install laser light link 2   Jamie           2                 2 2 2 2      
Build IOTA injector stands 1   Curt           1                 1 1 1 1      
Jerry's worklist below IOTA[3] 1         X                       1 1 1 1 1    
Help install beamtube in RF cavity 1   RJK supporting   X                         X X     x    
PXIE       DF KK CR DL CE EL   DF KK DL CE CR EL                
3.1 Two Week Shutdown[4] 1           X             X       1 1 1 1 1    
PIP 1           X                                  
Assemble next scrapers  2       X               X         1 1 1 1 1    
CMTS       DF KK CR DL CE EL   DF KK DL CE CR EL                
Accept CM9 into building 1   Overall priority #1     X X             X X X X   1            
Other                                                
Shielding Block Inventory 3         X                                    
Power distribution for coupler test stand 2       x                         2 2 2 2 2    
Fix hydraulic lifts used to install FAST beamline magnets 3   Parts repair kit is taped to lift.       APC  FAST/IOTA Technician                     3 3 3 3 3    
UHV + PF Clean hardware and beamline installation parts 1         Debby           X X         1 1 1 1 1    
Assist TD HTS in Meson DB 1               x                              

[1]
FAST / IOTA

1 Lambertson
2 IOTA Kickers
3 Other IOTA

Lambertson:

End plates should be available to be picked up middle of next week. Vendor will let know if they're available sooner

Cores still at vendor plating

Assembly was discussed

 Kickers:

Working on getting vacuum chamber produced. Ordered Chinese tube. Continued talking to other companies

Continued trying to figure out how to make parts in-house

Work continues on getting rolling machine operational

Working on Bi-metal components

Electrical:

Kermit will get together with Ron to order heat tapes for RF modules, electrical plugs

Additional cables need to be pulled

 

LCW:

Andrew and Ron making progress. Headers have been setup, except for vertical one. Marking places for support arms. Talking to fire department for permit

All flow meters should be here by Feb20, before they need to be installed

RF Cavity:

Work continues on RF cavity modifications/additions

Vacuum:

Darren: waiting for quote for electropolished washers. Rick has been helping with cleaning at CMTF and leak checking BPM housings

Spool pieces for girder 7 are at the shop. Waiting for flanges for girders 8 and 3

Req. has been placed for silver plating for first dipole chamber. Working on procurement of additional hardware/flanges

Sextupole:

Working with Greg Bulat on fabrication/machining process
[2]
FAST / IOTA

1 Lambertson
2 IOTA Kickers
3 Other IOTA

Lambertson:

End plates  are in box ready for H degas
 Kickers:

Working on Bi-metal components

Electrical:

Kermit will get together with Ron to order heat tapes for RF modules, electrical plugs

Additional cables need to be pulled

 

LCW:

Andrew and Ron making progress. Headers have been setup, except for vertical one. Marking places for support arms. Talking to fire department for permit

All flow meters should be here by Feb20, before they need to be installed

RF Cavity:

Work continues on RF cavity modifications/additions

Vacuum:

Darren: waiting for quote for electropolished washers. Rick has been helping with cleaning at CMTF and leak checking BPM housings

Spool pieces for girder 7 are at the shop. Waiting for flanges for girders 8 and 3

Req. has been placed for silver plating for first dipole chamber. Working on procurement of additional hardware/flanges

Sextupole:

Working with Greg Bulat on fabrication/machining process
[3]
Jerry's Craig work
- assist with Cryomodule removal/installation as required at CMTS1

Help Raul with his RF beamtube rigidity fixtures
[4]
PIP II Work
Plans for weekly access day (Th 3/29)
Cave to remain open until late in the day today
RF calibration studies ongoing
Pinch guards for M71 scrapers
Continuation of scraper limit switch retrofit
Working with M61 and M71, we’ll see how far we get
There is a desire to retrofit the out limit switches of the old scrapers also
M71 right and bottom motion control will not be done this access
MPS front end reboot
Vacuum burst work with RFQ tuner side ports
[5]